Will the proposed bridge have two lanes and a sidewalk?
Yes, the proposed configuration is two 11-foot lanes with 2-foot shoulders and a 5-foot sidewalk on the east side of the truss.
Will you need eminent domain to get the property you need?
We are working with the affected property owners to acquire the necessary right of way through temporary and permanent easements.
When will this project be out for bid?
The project is currently projected to be advertised for Spring 2022 construction.
I was hoping for a more modern design like River Street or Oak Street but at least a two-lane bridge will be nice.
A truss was chosen due to the hydraulics of the river and inability to raise the profile of the road to allow enough clearance for a multi-girder bridge.
Glad to see that the temporary bridge is finally going to be replaced. Also, that the alignment is being corrected.
Thank you for your support.
As the Batavia City Historian and also a resident of a nearby area, I am following this project with considerable interest. Assuming the new bridge will have two lanes, the improvement in traffic flow will be greatly appreciated.
The proposed bridge will have two lanes. Thank you for your support.
https://www.baileybridge.com/
This is the style of the existing bridge.
Yes, the proposed configuration is two 11-foot lanes with 2-foot shoulders and a 5-foot sidewalk on the east side of the truss.
Will you need eminent domain to get the property you need?
We are working with the affected property owners to acquire the necessary right of way through temporary and permanent easements.
When will this project be out for bid?
The project is currently projected to be advertised for Spring 2022 construction.
I was hoping for a more modern design like River Street or Oak Street but at least a two-lane bridge will be nice.
A truss was chosen due to the hydraulics of the river and inability to raise the profile of the road to allow enough clearance for a multi-girder bridge.
Glad to see that the temporary bridge is finally going to be replaced. Also, that the alignment is being corrected.
Thank you for your support.
As the Batavia City Historian and also a resident of a nearby area, I am following this project with considerable interest. Assuming the new bridge will have two lanes, the improvement in traffic flow will be greatly appreciated.
The proposed bridge will have two lanes. Thank you for your support.
https://www.baileybridge.com/
This is the style of the existing bridge.